Tuesday, 16 May 2017

Poltocsa - the day after the vote and a week before the building work starts

13 February 2017


Diospi Suyana building engineer Udo Klemenz and me discussed important broadcast technical needs for the planned FM radio tower construction in Andahuaylas.

After the surprising majority vote from the local community of Poltocsa (see my previous blog of 12 February), the building works are planned to start next Monday.  Diospi Suyana contracted an external construction company to manage the project, and they will keep Udo in the loop of the building progress through regular photo reports.  Our tower supplier ICESE will construct the 36m free standing tower after the 3m security wall has been erected and the site is secure.


To the right of the existing towers overlooking Andahuylas is the transmission site for Diospi Suyana

Regards,
Chris

Original Diospi Suyana post by Dr Klaus John;