The Diospi Suyana transmission “site selection team” (Klaus, Udo, Doris and me) again drive back to Andahuylas (about 5 hours’ drive west of Curahuasi) and then onto Chincheros (a further 2 hours’ drive on from Andahuylas).
On this trip we firstly inspected the Andahuylas FM Tx site civil construction work by our subcontractor, as overseen by Udo Klemenz.
I am standing in front of the Andahuylas transmission site tower foundation excavations. |
Udo reported the following regarding Andahuylas: “– we can definitely be pleased with the progress. The four tower pits dug in rocky subsoil, in which the foundations for the tower will be laid, have been excavated and are currently being reinforced.”
The steel tower foundation bolt template is in place awaiting the rebar steel mesh and then the concrete pour. |
All excavations (some 2.5m deep) are in difficult rocky ground and are done by hand – unthinkable in developed countries. |
In my following post I continue with day 2 news from Chincheros Province.
As an adjunct to Udo’s weekly building report, we also report on a development with the Curahuasi broadcast site. The local electrical utility Electro Sur, are finally erecting the poles up to our broadcast site. Note the way the pole is being rigged into place (i.e. using the nearby tree!).
Electro Sur at work in Curahuasi running power to our new broadcast site. In the background you can see the Colegio Diospi Suyana. |
Chris