26 May 2017
It is 98 days until the 10th Anniversary
celebrations at Diospi Suyana. The
countdown is on to getting the Diospi Suyana FM transmission sites finished
beforehand if possible. We will do our
best!
Casabamba: a 2.6m deep test pit has been dug for the tower
soil to be analysed by the geotech enabling the tower foundations to be
designed. We hope to award the contract
for the structural work within the next few days. The 50m tower for Casabamba has been
purchased from our now established supplier ICESE SAC based in Lima.
Puerto Maldonado: the subcontractor has started excavating
the large four individual foundations for our 50m high tower, also from our
supplier ICESE SAC. Being the rainforest
region, it is hot and humid and there are a lot of biting insects. It’s not everyone’s cup of tea.
Manually excavating soil geotech pit for the 50m tower foundations in Casabamba – it would be unthinkable to do this by hand in affluent places like Australia. |
In the Amazon rainforest near the city of Puerto Maldonado, the foundations are being dug for the Diospi Suyana's next 50m high FM broadcast tower. |
Here is an AutoCAD drawing plot of our ICESE SAC 50 meter high free standing lattice steel towers for Casabamba and Puerto Maldonado. |
Chris